2026-10-23 · Pressure Vessels · Vistra Inspection Services and Consultants
Use this checklist when preparing the QAP for a pressure vessel or when planning TPI visits.
1. Before fabrication
- Design calculations and GA drawing approval
- Material identification and MTC review for shell, heads, nozzles and flanges
- WPS/PQR and welder qualification review
- NDT procedures and technician qualifications
2. During fabrication
- Plate marking, cutting and edge preparation
- Dished end thickness and profile after forming
- Long-seam and circ-seam fit-up
- Back-gouging and root-pass checks
- Nozzle orientation, projection and elevation
- Radiography / UT of seams as per joint efficiency
3. Heat treatment and testing
- PWHT procedure and chart review
- Hardness checks after PWHT where required
- Hydrostatic test at the calculated test pressure
- Pneumatic test safety precautions, if applicable
4. Final
- Final visual and dimensional inspection
- Painting and DFT
- Name-plate stamping
- Manufacturer's data report and dossier